All six lanes of the TF1 are fully open as from 7am this morning. There is still more work to do over the next few months (they gave March as a final completion date recently), specifically final surface coatings, but the six lanes are now operational!
Next week it's planned to put the new Alisios I bridge in service, which will give direct access from the TF1 to the TF2 (from the south towards La Laguna).
Canarias24Horas